Completion Certificate Delayed By Missing Documentation

The work was done. The paperwork was not. Six months later, the certificate finally arrived.

What happened

An extension was finished, signed off practically, and the family moved in. The Completion Certificate did not arrive. When chased, Building Control listed five outstanding items — none of them physical work, all of them paperwork.

How it was discovered

When the homeowners tried to remortgage. The mortgage offer was withheld pending the certificate.

The consequences

Six months of letters to the builder, the engineer and the gas installer. Eventually all the trade certificates were assembled and Building Control issued.

What homeowners can learn

Do not pay the final invoice until the certificate is in your file. Leverage disappears with the cheque.

Coming soon

The Homeowner Survival Guide

47 pages. Real photos. The 12 mistakes we see homeowners make every week — and how to spot them before they cost you thousands. Currently in the final edit — available shortly.

Free Download

Get the Homeowner Survival Guide

47 pages. Real photos. The 12 mistakes we see homeowners make every week — and how to spot them before they cost you thousands.

No spam. Unsubscribe any time. We never share your address.